The Supreme Court Indictment of the Environment Impact Assessment of the Mopa Airport and Lessons to be Learnt
SC Stays EC of Proposed Mopa Airport
On 29th March 2019, the Supreme Court (SC) suspended
the environment clearance (EC) granted to the proposed Mopa airport in Goa, due
to serious lapses in the impact assessment, including non-disclosure of vital information
by the project proponent (Government of Goa) and abdication by the Expert Appraisal
Committee (EAC) of the environment ministry of its role and function to
appraise the environmental impacts and mitigation plans and recommend or deny
the EC based on this.
The essence of the problem can be captured just four words
used in the judgement, that the EIA (Environmental Impact Assessment) of the
project is “parsimonious with the truth”.
A more pithy and terse but sharp and hard-hitting summary would be
difficult to find.
Unfortunately, what the judgement says about the Mopa EIA is
true about many, if not most of the EIAs for such large infrastructure projects.
Proposed Airport and Trees to be felled for it. Photo Courtesy https://m.dailyhunt.in
A Far-Reaching Judgement
Indeed, that is what makes the Mopa judgement so important –
that it identifies and clearly spells out key problems with the entire process
of environmental clearances for infrastructure projects. It also lays down principles
and guidelines for ensuring that the spirit and letter of environmental laws are
implemented, or, as the judgement points out, for upholding the “environmental rule
of law”. These points, a few of which we will highlight here, have the
potential to bring back on track the environmental clearance process which has
been distorted to the point where environmental protection has become the least
important aspect in the process, a process that has been reduced to rubber-stamping
project clearances no matter the nature and extent of their social and environmental impacts.
This far-reaching implication of the judgement is probably
what caused NITI CEO Amitabh Kant to write an angry commentary on the
judgement, ( “The
Need to Mope About Mopa”, ET April 15, 2019) calling the verdict a “dangerous
precedent”. It certainly is a dangerous precedent – dangerous to those who see environment
as merely an obstacle in the path of development (whatever the latter may
mean), and who have been pushing and bending the implementation of
environmental laws to get away with blatantly violating and ignoring environmental
concerns. Kant’s article clearly reflects the unease that an institution as important
as the SC has called out the terrible flaws and called for addressing them. Kant’s
articles is mostly a series of specious arguments and has been ably addressed
by eminent environmental lawyer Ritwick Dutta in his rejoinder “When
Wings were Rightly Clipped” (ET April 29, 2019) so we won’t get into it.
But we will later bring in some points that Kant makes to highlight the
problems in the EC process.
Critical Points in the Judgement
Complete Disclosures at Application Stage a Must
Coming back to the important points made by the judgement,
the very first point is that full and proper information should be given right
at the stage of application for EC, that is, in the Form 1 (and Form 1A).
Often, the project proponents leave questions blank, or provide inadequate or
even misleading information in the this Form. Sometimes, the information is subsequently
provided in the EIA. This judgement has highlighted that nondisclosure at Form
1 stage cannot be remedied by disclosure at EIA stage, and that
“failure on part of the project proponent to make mandatory
disclosures stipulated in Form 1 under the 2006 notification…must have
consequences in law.”
The reasoning behind this is also very important, namely,
that the
“failure on part of a
project proponent to disclose material information in Form 1 …has a cascading
effect ..”
because the TORs are based on Form 1, and the EIA has to be
assessed against the TORs. Moreover, the EIA Notification gives the power to
the EAC (and the SEAC) to reject the project at the application stage itself in
case it is seen as severely impacting the environment. Information given in
Form 1 would play a big part in this consideration. Thus, non-disclosure or
wrong disclosures in Form 1
“bypasses the authority of the EAC and SEAC to reject an
application at the preliminary stage and cannot be countenanced.”
Proposed Airport and Trees to be felled for it. Photo Courtesy https://m.dailyhunt.in |
EAC Must Apply Mind to Environmental Aspects
An important point made by the judgement is that
“the EAC betrays a lack of comprehension of the true nature
of its function under the 2006 notification. The EAC has failed to consider
relevant circumstances bearing on the environmental impact of the project and
has instead considered circumstances extraneous to its function.”
This unfortunately is
the rule rather than the exception in most EACs and their deliberations. In the
Mopa case for example, the SC judgement lists the six points considered as
reasons by the EAC to recommend clearance to the project, and these include
issues like project is in public interest, delays in land acquisition etc.
whereas no environmental factors are listed.
Indeed, it is not the function
of the EAC to look at whether a project is in public interest (one presumes
that if it was not, this fact would have been identified at the pre-feasibility
stage itself and the project would never have come to the EC stage), and more
importantly, use that as a reason (or excuse!) to overrule all environmental
impacts, objections. The main function and role of EAC is to assess the environmental
impact and appraise the project from the sustainability angle. As the judgement
rightly says, this
“analysis of the EIA report is, to say the least, sketchy and
perfunctory and discloses an abdication of its functions by the EAC.”
The judgement then order
the EAC to re-examine the project, an exercise “primarily … for the EAC to
carry out in its expert decision making capacity.” If all the EACs just simply
adhere to this role and function as has been mandated for them by the EIA
Notification 2006, it would dramatically alter the EC process in favour of
environmental protection, as is the intent of the law.
NGT Must Carry Out Merits Review
As the judgement points out
“The mix of judicial and technical members envisaged by the
statute is for the reason that the Tribunal is called upon to consider
questions which involve the application and assessment of science and its
interface with the environment.”
Thus, the NGT is supposed to examine the appeals in front of
it not just on the grounds of law but on the grounds of merits and substantive questions
of environment. The judgement points out that
“In failing to carry out a merits review, the NGT has not
discharged an adjudicatory function which properly belongs to it.”
And that this constitutes
a failure of the (checks and balances in the) EC process. Such failure of the
NGT to carry out an effective merits review is seen in many other cases. For
example, consider the OA 487/2015 which called on the NGT to require the Ganga
Waterway (National Inland Waterway 1) to seek environmental clearance as at
least the dredging component fell within the ambit of the EIA Notification
2006. The NGT heard the matter for close to three and half years, and at the
end merely ordered that the MoEFCC should state its stand on whether waterways
needed EC or not. (See here
for a commentary on that order by Avli Verma of Manthan).
The NGT is supposed to
act as a check to ensure that the EAC and MoEFCC do justice to the spirit and letter
of the EIA Notification 2006 to ensure proper scrutiny and clearance only if
environmental protection is ensured. A failure by NGT to carry out such merits
review, and in a time bound manner, is detrimental to the larger goal of
protecting the environment and ensuring sustainable development and allows the
flawed processes in the EC process to continue.
In his article mentioned earlier, Kant says “And, yet, the
apex court continues to treat the environment and economic development as
binaries. Neither does it provide a means to reconcile SDGs [Sustainable Development
Goals] in the context of the Mopa airport, nor does it call for a proper cost
benefit analysis.”
But Kant forgets, or ignores, that this (reconciling SDGs in
context of infrastructure development) is not the role of the SC or the
judiciary. The SC had to intervene precisely because of the complete failure – in
fact, a deliberate, considered abdication of responsibility of protecting the
environment – by the Government and its specific institutions like the MoEFCC,
EAC that are tasked with the job.
Indeed, what the Mopa order has done is in fact laid down principles and ways
of operating that will ensure that the existing systems (like EAC) work in way
that proper reconciliation of developmental and environmental goals is done,
and to ensure the “environmental rule of law”.
Bona Fides of Those Raising Objections
A very critical observation of the judgement is that it has
considered it
“appropriate to record a finding on the bona fides of
the appellants before this Court. It was briefly urged by the respondents that
the appellants have invoked the jurisdiction of this Court based on a personal
agenda and consequently, the present appeal is liable to be dismissed. This
argument cannot be accepted.
“Vague aspersions on the intention of public-spirited
individuals does not constitute an adequate response to those interested in the
protection of the environment.”
This is really important as often, project promoters,
Government and vested interests attack anyone who raise objections, who question
projects, who talk of environmental impacts, by abusing them, by casting aspersions
on their motives and means etc. The SC judgement has done well to remind all that
there is an important role for such public spirited individuals and that casting
aspersions on them cannot be a defence against the issues raised by them. These
need proper answers from governments and
project authorities.
It may be pointed out, for example, that the EAC responsible
for assessing River Valley and Hydropower projects had actually decided in its
meeting of 30th Dec 2016, that it will “not take any cognizance of
such representations received from the any Civil Action Group during final
appraisal”, because such representations “have an anti-development
attitude so that the projects are kept on hold or delayed. This has financial
implications to the developers in particular and to the nation in general.”
Excellent Tutorial
Lastly, an unrelated but a very interesting aspect of this
judgement. The judgement explains in detail the entire procedure for a project
to obtain environmental clearance under the EIA Notification 2006. In that, for
any student who wants to understand the said notification and the procedure for
environmental clearance, this is an excellent tutorial and a wonderful first learning,
that too from two judges of the Supreme Court.